# The Ten Steps a Damaged Unit Goes Through Before You Get It Back

> Structure first, cosmetics second, systems tested last. Ten steps, and the two that add calendar days are **parts lead time** and **supplement approval**, neither of which is fully ours to control.

## What are the steps in an OCRV Center repair?

Intake, written scope, authorization, parts, teardown, supplement, structural correction, refinish, reassembly with testing, then delivery with the file. Every step happens at the Yorba Linda shop, and structure is verified before any cosmetic work begins, which is the part owners most often get sold in reverse.

- Ten steps, performed in a fixed order for a reason
- Written repair estimate is $150 and credited to authorized work
- Deposits apply at authorization above $2,000
- Nothing is repaired until the scope is agreed in writing

### Key facts

| Item | Value |
| --- | --- |
| Steps | 10 (Intake through delivery, fixed sequence) |
| Written estimate | $150 (Credited in full against an authorized repair) |
| Deposit trigger | $2,000 (50 percent at authorization above that figure) |
| Second deposit trigger | $10,000 (Additional 25 percent when parts arrive) |
| Longest variable | Parts lead time (Days on a seal, months on a discontinued cap) |

Repair sequence is not a marketing decision. It is a physical constraint. A panel gap cannot be set on a body that is sitting on a bent rail, and paint cannot be evaluated on a wall that is going to move when the slide is reinstalled. Get the order wrong and you produce a unit that photographs beautifully and comes back in four months.

What follows is the actual order, including the two steps nobody enjoys. Read the parts step and the supplement step carefully, because between them they account for most of the calendar time on a large job.

## Steps one and two: intake and the written scope

Intake is a walk of the whole unit with a light, a tape and a camera, plus a tap test along every laminated panel within reach of the damage. The tap is the part owners find odd and it is the part that changes estimates, because a hollow response two feet from a visible crack means the bond line let go further than the impact mark suggests. Data plate, serial, floor plan and prior repair history all get recorded here.

The written repair estimate follows. It costs $150 and it is credited in full against an authorized repair, so you pay for it once if you proceed. If a claim is open, the same scope goes to your carrier in the format their estimating system expects, with photographs attached and line items priced against the posted rates rather than against an automotive labor guide.

1. Full unit walk with damage mapped by side, height and station
2. Tap test across laminated panels adjacent to visible damage
3. Data plate, serial and floor plan captured for parts ordering
4. Written scope produced, priced and photographed

## Steps three and four: authorization and parts

Authorization is a signature on a scope, not a verbal go ahead, and it is where the deposit applies. Fifty percent is taken at authorization on anything over $2,000, with an additional twenty five percent when parts land on anything over $10,000. Special order parts require a full deposit at order and that deposit is not refundable, because a molded cap ordered against your serial number cannot be sold to anybody else.

Then parts, which is the step that decides your calendar. A Lippert rail or a Dometic control board is days. A discontinued fiberglass cap, a Hehr window frame for a 1994 coach or a formed composite section from a low volume builder can be months, and we say which one you have before you sign rather than after. Where a part is unavailable, the alternatives get quoted as separate options: mold work, fabrication, or repair with an accepted witness line.

## Steps five and six: teardown and the supplement

Teardown is where the job becomes real. Skin comes off, insulation comes out, and the framing, substrate and wiring behind it are seen for the first time. Almost every recreational vehicle job grows here, and the honest reason is that nobody can see through a bonded wall. Wet lauan crumbles at the fastener holes. An aluminum cage member that absorbed the impact shows a kink invisible from outside. Water that entered at a roof seam leaves a stain trail running downhill to a place nobody suspected.

Everything found gets measured, photographed with something in frame for scale, and written as a supplement before it is repaired. This is the single most common place a claim stalls, and the cause is nearly always documentation quality rather than disagreement. A supplement that shows a tape across rotten decking with the slide opening visible behind it gets approved. The same finding described in a sentence gets questioned.

> **insurance:** No panel comes off an insured unit before the scope is agreed. Unauthorized teardown is the fastest route to an owner paying out of pocket for work a carrier would otherwise have covered.

## Steps seven and eight: structure, then surface

Structural correction comes first and it is verified rather than eyeballed. A body on frame coach goes on the rack with anchoring at the manufacturer's points, gets pulled, and is measured against published dimensions with the comparison sheet printed for the file. A unibody van has no separate frame, so the whole exercise is measurement against factory control points, and the printout is the deliverable. Body mounts, subframe members and slide openings all get checked before the first panel goes back.

Surface work follows in its own order: metal and composite repair, substrate priming, block sanding, then the booth. Color is matched with a spectrophotometer and confirmed with a sprayed and cured spray out card held against the actual panel in daylight, because a twelve year old coach does not match its own paint code. Blend zones are decided before the gun is picked up, and on a full coach the masking is most of the labor.

## Steps nine and ten: reassembly, testing and delivery

Reassembly is followed by testing, in that order, because a slide that cycles on the bench proves nothing about a slide bolted into a wall that has just been rebuilt. Rooms are cycled twice through full travel with the second cycle recorded. Any seam, opening or roof penetration that was disturbed gets water tested with cameras inside and out. LP is leak checked with a manometer where lines were touched, and electrical circuits are loaded rather than simply energized.

Delivery is a walk with you, not a phone call and a key handoff. You get the file: intake photographs, teardown frames, the measurement comparison sheet where structural work was involved, the approved scope, the supplement history and what was actually performed against it. Final balance is due at pickup. If anything on the unit is not right, the walk is when to say so, standing next to it.

## What you actually decide, and when

Owners have four real decision points and it helps to know them in advance. At authorization you decide scope, which includes whether to fold in work that is cheap while the wall is already open. At parts you decide between waiting for a factory panel and taking a fabricated alternative. At supplement you decide whether to pursue a line the carrier pushed back on. At delivery you decide whether the work is accepted.

Everything between those points is ours. You are not expected to chase your adjuster, follow up on a back ordered rail or interpret a betterment deduction. That is what the claims side of the shop exists to do, and it is why the coordinator who writes your scope is the same person who takes the adjuster call.

**Decision points and who owns them**

| Step | Your decision | Ours |
| --- | --- | --- |
| Scope agreed | Approve, add or defer line items | Write and price the scope |
| Parts | Wait for factory or accept fabrication | Source, quote lead time, disclose backorders |
| Supplement | Pursue or drop a contested line | Document, justify and file it |
| Delivery | Accept the work | Test, walk it with you and hand over the file |

## Questions and answers

### Why can't the paint be done at the same time as the frame work?

Because pulling structure moves everything attached to it. A panel aligned and painted before a rail is corrected will end up with a different gap, a stressed seal line and sometimes a cracked bond. Refinishing is the last thing that happens to a surface, and every shop that reverses that order produces repeat work.

### Can we skip teardown and just repair what is visible?

On a cosmetic scratch, yes. On any impact that broke a laminate skin, no, because the bond failure behind it extends past the mark and a surface repair over separated substrate will lift within a season. We will tell you plainly which category yours is in, and the tap test at intake is what settles it.

### How will I know where my unit is in this sequence?

You get contacted at each transition rather than on a schedule, because a fixed weekly call is usually a call with nothing in it. Transitions are authorization, parts landing, supplement filed, structural sign off, booth entry and ready for delivery. If a step stalls, you hear about it when it stalls, not at the next update.

### Can I add work after the repair has already started?

Usually yes, and it is often the cheapest moment to do it, since teardown labor is already paid for. Adding a cabinet refacing while an interior wall is open costs a fraction of doing it later. What we will not do is fold owner requested upgrades into an insurance scope, because they are not part of the loss.

### Who checks the work before it is handed back?

The department lead who performed it signs off, then a second lead inspects across departments, which catches the things a person who has stared at a panel for three days stops seeing. Structural work is signed against the measurement sheet rather than by opinion. Then the delivery walk happens with you present.

### When is the balance due, and what forms of payment work?

The balance is due at pickup, after the delivery walk. Deposits already paid come off it. Card payments over $1,000 carry a 3.5 percent surcharge, which is disclosed at authorization rather than discovered at the counter. On an insurance file, the carrier's payment and your deductible are reconciled before pickup.

---

Source: [OCRV Center](https://ocrv.me/our-process/). Last verified 2026-07-29.